email icon Email updates  mzl jbprrjhp x Nixle alerts


free vector road closed ahead sign clip art  Road Closed Ahead Sign clip art hight
Shelby Township Road Projects --24 MILE ROAD UPDATE--

As Ric-Man Construction continues the Detroit Water and Sewerage Department 42-inch water main beneath 24 Mile Road in Shelby and Macomb townships, there remains three sections of road unpaved in Shelby Township.


These sections will remain unpaved until temperatures reach into the high 40s on a consistent basis once asphalt can be laid.


The sections will remain unpaved as crews install cross-connection valves between the new 42-inch main and the existing 36-inch main that runs parallel to the new pipe.


There will be temporary road closures posted by the Macomb County Department of Roads as these connections are installed. Ric-Man officials hope to have the first of these connections installed near the Macomb Orchard Trail by Christmas Day.


Crews will then move to install the valve near the Cherry Creek Golf and Banquet Center with hopes to have that complete by mid-January. The final valve connection will be installed near the 24 Mile and Schoenherr roads intersection by mid-February.


Along with the three stretches of unpaved roadway, crews will also finish pavement in the Mound and 24 Mile roads intersection in the spring and restripe the roadway to accommodate for a left-turn lane for eastbound and westbound traffic


Maintenance of the temporary roads will be performed by Ric-Man Construction. If you see any portions of the roadway in need of maintenance please contact the Shelby Township Supervisor’s Office at 586-731-5154.


Ric-Man Construction issued a chart outlining all planned phases of the project as it relates to the phases' tentative start and end dates. That chart can be found  here

Link to MCDR 24 Mile Road water main construction/closure notices Read More...
DTE Energy logo
DTE to conduct vegetation management in Shelby Township
Throughout 2015, crews from DTE Energy will be conducting vegetation management throughout Shelby Township.

There are five areas that will be impacted between September and December 2015. Please see the letter from DTE Energy below for more information on the program and check the maps to see if your home falls within the affected areas. For more information contact DTE Energy at 313-235-4141 between 8 a.m. and 4 p.m. Monday through Friday.

water drop
DPW releases 2015 edition of The Pipeline
The Shelby Township Department of Public Works is pleased to announce the 2015 Issue of "The Pipeline".  Presented to you by DPW Director Dave Miller on behalf of the DPW, "The Pipeline" is the Township's Annual Report regarding the safety and quality of your municipal drinking water. 
To view the 2015 issue click on the following link: The Pipeline